Summary
A long-awaited repaving of Cass Street with new ADA curb ramps is funded and contracted, timed after Cal Am's water main replacement. Bus routes will be detoured during roughly ten weeks of construction.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Sep 1, 2026.
Impact analysis
$374,525.11 added from Measure P/S plus a $1,610,351 contract — bids came in below the $2.1 million estimate.
Drivers, bus riders and pedestrians on a core downtown connector street.
Businesses and commuters face construction disruption for about ten weeks.